This is my conversion settings.
I want to confirm the following questions before I hit the convert button:
Some projects manage their start and end dates only in Jira field and some only in Gantt Chart filed.
1. What happen to the values in Jira start and end date fields when there is no value in Gantt Chart app's start and end dates field? will the values in Jira field remain?
2. If there is no start and end date field in Jira issue and start and end states values are in Gantt Chart app, will the value in Gantt chart appear if I add the start and end date field back to Issue after the conversion? (or do I have to do it before the conversion?)
Hello @Hsinyi Hung ,
Some projects manage their start and end dates only in Jira field and some only in Gantt Chart filed.
1. What happen to the values in Jira start and end date fields when there is no value in Gantt Chart app's start and end dates field? will the values in Jira field remain?
Unfortunately, you can only choose whether you want to override existing Jira field data or Abandon WBS Gantt-Chart unique data when you execute the data conversion.
Here are the results of both options.
WBS Gantt-chart field data(before conversion) | Jira field data(before conversion)| → Jira field data(after conversion)
Override existing field value
① blank | blank |→ blank
② have data | blank |→ WBS Gantt-chart field data
③ blank | have data |→ blank
④ have input data | have data |→ WBS Gantt-chart field data
Abandon WBS Gantt-Chart unique data
① blank | blank |→ blank
② have data | blank |→ blank
③ blank | have data |→ Jira field data
④ have data | have data |→ Jira field data