Tempo JIRA sync not working

Zoe Hutchinson March 5, 2024

Hello, I am trying to set up the Jira/Tempo sync as per this article https://help.tempo.io/planner/latest/syncing-with-jira

I have mapped the fields - see screenshot - Capture.PNG

but when I come to plan time in Tempo & sync with JIRA I get this error message 

278bb079-0d4b-4eb0-b074-3ec4e627821f.png

It seems like the sync doesn't like the fields I've chosen but it's not clear from the error message. Can anyone help?

1 answer

1 accepted

0 votes
Answer accepted
Susan Wu
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 5, 2024

Hi @Zoe Hutchinson 

From your screenshot, it seems that your Start Date and End Date are Jira custom fields, which are not assigned to the screens used in the project(s) you are using for plans sync.

If you still have problems, please contact Tempo Support for further investigation.

https://tempo-io.atlassian.net/servicedesk/customer/portal/6

Best regards,

Susan Wu

Tempo Product Expert

Zoe Hutchinson March 19, 2024

Thank you! I hadn't noticed the capitalisation on Start Date, so hadn't realised it was a custom field. 

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events