Release - Sprint relationship in Rapid Boards ??

V December 31, 2012

Hi Atlassian Support,

We are Green Hopper version *6.0.8*

Is there any way that we can have a parent-child (release-sprint) relationship in the rapid boards, As it was available in classic planning board?

If So, can we have a *Release Burndown chart* in Rapid board that shows the Story point Burndown, *sprint* wise (child.)?

Please help us. Your quick response is much appreciated.

Thanks,

Venkat

2 answers

1 accepted

0 votes
Answer accepted
Faisal
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 31, 2012

Hey Venkat,

I have responded to the support request that you have raised in our system, and apparently my findings shows that it may not be possible to have Sub tasks estimation to be displayed in the Burndown Chart. A related Story had been raised in our system earlier:
- Show sub-tasks information on Sprint Report

I hope that the clarification on the matter helps.

Cheers!

0 votes
V December 31, 2012

One more question Can we create a Release and a sprint under it in Rapid Board?