Hello,
What can be the solution for such case:
1. We have cadence about 2 weeks long and four teams.
2. Some features estimates are more than two weeks.
3. Features have cross-teams dependencies which should be displayed on the board
3. We tried to put feature in the cadence feature should be finished. But in this Finish-to-start dependencies can be set incorrect as we don't see Feature start.
The questions:
1. What is the possible solution for such case?
2. Is it possible to put feature in a few cadence or show feature start date/cadence somehow?
Thanks!