How can I create a task/s, based on the status change of another task

Adrian Rawlins September 24, 2018

I have a workflow where two tasks are created upon a form being edited, but then I want a further 5 tasks to be created, once one of the original tasks is resolved.

1 answer

0 votes
Scott Harwood
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 25, 2018

Hi Adrian,

Thanks for getting in touch. You can use an issue transitioned trigger, followed by 5 create issue actions. For example:

 

Screen Shot 2018-09-26 at 3.16.37 pm.png

 

Let me know if that would work for you.

Thanks,

Scott.

Adrian Rawlins September 26, 2018

Hi Scott,

 

Thank you for your reply much appreciated.

I need this to be generated of the back of a task being completed, not and issue status changing.

This is what I have done, but it doesn't work.2018-09-26_11-05-19.jpg

So two tasks generated from issue being edited. Then 3 tasks generated once one of the original two is resolved.

 

Thanks

 

Adrian

Suggest an answer

Log in or Sign up to answer