Why do I see two statuses in my backlog when I've only designated one?

Dylan Kogut June 9, 2022

Hi, 

I've selected only Status: "New Request" to be associated with the Backlog yet "Ready to Start" appears above it.

 

How can I remove this to just show "Backlog" IE only Status: "Ready to Start" ?

 

Screen Shot 2022-06-09 at 4.51.09 PM.pngScreen Shot 2022-06-09 at 4.53.14 PM.png

1 answer

1 accepted

2 votes
Answer accepted
Ivan Lima
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
June 9, 2022

Welcome to the Atlassian Community.

By design, it shows the name of the first column of your Kanban board. I don't believe you can change that. Have a look at https://support.atlassian.com/jira-software-cloud/docs/use-your-kanban-backlog/

Suggest an answer