With the current workflow, we have set up custom resolution states and resolution values, We have 3 states of resolutions:
- QA validated
- Pre-production
- Done
All of our sprints do not capture the stories as "completed" if we do not reach Done. We would like to count the story points if we reach "Pre-production" but looks like Jira is only counting "Done" as the complete state.
Can that be configured?
A sprint will consider an issue "completed" and count its story points if the Status of that issue is mapped to the right-most column of your board.
Can you show us the board setting that show the columns to which each status is mapped?
Thank you!
My mapping was 3 columns:
- ToDo
- In Progress
- In Review
- Failed QA
- Passed QA
- Pre-Pro
- Done
By which all of the statuses to the same column the points are captured properly! I created a TEST project with the right mapping and everything works perfectly now.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.