Why custom resolutions do not count story points?

pteyssedre May 8, 2022

With the current workflow, we have set up custom resolution states and resolution values, We have 3 states of resolutions:

- QA validated

- Pre-production

- Done

All of our sprints do not capture the stories as "completed" if we do not reach Done. We would like to count the story points if we reach "Pre-production" but looks like Jira is only counting "Done" as the complete state.

Can that be configured?
jira-report.png

1 answer

1 accepted

2 votes
Answer accepted
Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 8, 2022

A sprint will consider an issue "completed" and count its story points if the Status of that issue is mapped to the right-most column of your board.

Can you show us the board setting that show the columns to which each status is mapped?

pteyssedre May 9, 2022

Thank you!

My mapping was 3 columns:

- ToDo

- In Progress

- In Review

- Failed QA

- Passed QA

- Pre-Pro

- Done

By which all of the statuses to the same column the points are captured properly! I created a TEST project with the right mapping and everything works perfectly now.

jira-1.pngjira-2.pngjira-3.png

George Turnbull February 27, 2024

Does this work the same for Jira Data Center

Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
February 27, 2024