Why custom resolutions do not count story points?

With the current workflow, we have set up custom resolution states and resolution values, We have 3 states of resolutions:

- QA validated

- Pre-production

- Done

All of our sprints do not capture the stories as "completed" if we do not reach Done. We would like to count the story points if we reach "Pre-production" but looks like Jira is only counting "Done" as the complete state.

Can that be configured?
jira-report.png

1 answer

1 accepted

2 votes
Answer accepted

A sprint will consider an issue "completed" and count its story points if the Status of that issue is mapped to the right-most column of your board.

Can you show us the board setting that show the columns to which each status is mapped?

Thank you!

My mapping was 3 columns:

- ToDo

- In Progress

- In Review

- Failed QA

- Passed QA

- Pre-Pro

- Done

By which all of the statuses to the same column the points are captured properly! I created a TEST project with the right mapping and everything works perfectly now.

jira-1.pngjira-2.pngjira-3.png

Suggest an answer

Log in or Sign up to answer
TAGS

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you