Hello,
I am actually trying to export my epics into jira project. I have managed to do so but i got the "unable to parse date " error message.
I want my dates to be to this format : 12/04/2023 ( 12 april 2023 : day/month/year)
I have put this value in the export Jira manager :
And in my excel its configured like this :
Do you know what i am doing wrong ? What format date i should use in jira manager and csv to make it works?
Thanks in advance for your answers !
Regards
Hi Vigneux,
Did you try to make the 'M' as small, and add 2 more y's in the Jira format?
That will mostly work for the 'unable to parse date' issue.