Hi,
I would just need confirmation for this - Remaining Estimate field is not visible on create issue screen despite having Time tracking added on mentioned screen/issue operation? I can clearly see Original Estimate field when creating new issue but not Remaining Estimate as well.
Also, on new issue transition experience, once Time tracking is added, both remaining and original estimates are visible.
Cheers,
Tom
Hi Tomislav,
It wouldn't really make sense for it to be on the Create screen as you shouldn't be populating it during create, but it should be calculated when time is tracked/entered.
Hi @John Funk ,
Yeah, I definitely agree that it probably shouldn't be visible there but I didn't notice this before (probably as I never had to change it), and one client is asking about it as they are migrating from server so I just wanted to check.
Thanks!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.