No start date for task

genadijrazdorov January 15, 2020

Once touched Start date can not be reset to initial value of "No start date". Task with this value shows starting as of today on Roadmap page, which is convenient for not time scheduled tasks.

Is there a way to do this, or to suggest a added value for dates (today) to the Atlassian?

1 answer

1 accepted

1 vote
Answer accepted
Iago Docando
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 15, 2020
  • You could edit your edit screen and add the startdate field so you can modify it simply clicking on it. (3 clicks to delete the date)
  • You could add a transition to your workflow called "clear start date" or similar. make it start and end in the same status you want and add a postfunction that deletes the value for that field. (1 click to delete the date but more initial work editing the workflow)

Maybe there are better ways but this two are the ones that come to mind.