Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Jira with Tempo plugin: sometimes Jira is not reducing remaining estimate while working with Tempo.

Edited

Hello, Community!

We have a Jira project with Tempo plugin installed.
Our team members are logging time in Tempo.
I have noticed, that for some tasks the remaining estimate is not being changed, after a person logged some time in Tempo.
I have noticed, that this happens only to tasks which are in ToDo state, while if I have moved the task to In Progress - Tempo works as expected.


The questions are:

1. Is my observation valid?
2. Is it possible to force Jira/Tempo to reduce remaining time for a ticket residing in any status?

 

UPDATE:

Can be closed. The team member was manually changing the remaining estimate in Tempo's form while logging time in Tempo. They have a Hidden Fields section there where it is possible.