Issues not showing in current sprint after status update?

nishu.sharma
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
December 3, 2019

I added a few issues from backlog in current sprint. However, once I updated the status the issues are not showing in the current sprint nor in backlog.

Even though these are visible on dashboard.

 

Also, the issues from previous sprint have been carried foward and are showing in current sprint.

1 answer

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 4, 2019

That suggests that your board that the sprint belongs to does not have the current status of the issues mapped into a column.

Issues from previous sprints will carry over into new sprints when the issue is not "done" - Jira defines that as "not in the last column of the board, or having incomplete sub-tasks"