Hello,
After using tests as link between test execution and test case issues, we decide to use realizes.
It was so easy to create new links realizes in Jira trough import from CSV files.
Now, I would remove the old links (tests) between two issues. Is it possible ?
@Eric Vanderbeck You can't do it via CSV, you need to use a script (groovy) for example
Kind regards,
Moses
Many thanks for this fast answer !