How to interpret CFD if the tasks keeps accumulating?

Be it Sprints or Kanban, the CFD seems skewed, in that, over time, ALL tasks in DONE status since the beginning show up in the report, even if I have a shorter date range selected. Is that the intended behavior?

Attaching a screenshot of how it looks for me:

image2016-9-18 16:17:13.png

 

If this is not supposed to be so, I have a strong feeling that my project settings has a quirk as the reason for this. One thing I know for sure is that my project has a custom Workflow without any of the default Close/Reopen statuses or transitions. Could that be the reason?

1 answer

I see that the screenshot I added was not of a shorter date range, so here is one more:

image2016-9-18 16:44:18.png

(Please don't mind the changes in Legend at top-left — diagrams from different boards)

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Jan 08, 2019 in Jira

How to Jira for designers

I’m a designer on the Jira team. For a long time, I’ve fielded questions from other designers about how they should be using Jira Software with their design team. I’ve also heard feedback from other ...

1,084 views 4 9
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you