I have not completed the previous sprint before starting a new one. How can I complete the last sprint now after the new one has started?

1 answer

0 votes
Jack Brickey
Community Champion
October 15, 2019

Disclaimer: I haven’t played with parallel sprints in a long time.

Assuming you have manage sprint permissions, I believe you should be able to do this on the Reports screen, e.g. sprint burn down. Choose the previous sprint. 