This is probably very straightforward and sure I am missing something, but how do I add an existing Epic to the Timeline?
I am just now starting to use Timeline, I have a software company managed project. I have looked at the tutorial, but this only shows me how to create a new Epic and child issues from the Timeline. However, I am wanting to pull in existing Epics and child issues to the Timeline.
Check your board filter, it may have a field like "team" which assigns issues to board. For an Epic update the same field. e.g. if project filter is like Team="ABC" then for epic update team="ABC".
Hello @Jason Chayer
With the Standard subscription you have access to the "basic" Timeline feature. That means you are constrained to a single project. The Timeline feature will be available when you are viewing a Board, and should show the Epics that are within the scope of that board's filter.
Is that not the experience you are having?