How to add estimation to the subtask?

We have set the board to use Original time estimate e.g. in work hours, days and weeks. 

So how do I add estimation to the subtasks? I cannot do it during the subtask creation or when I edit existing subtask or even if I go the subtask details. 

I don't see any option to add Estimation like I can do it with the regular task. 

1 answer

This widget could not be displayed.

Make sure the "timetracking" field is

a) Not hidden in the field configuration for the sub-task types

b) On the sub-task issue types' "create" and possibly "edit" screen

But.  Don't.  JIRA Software (JIRA Agile) does NOT take account of the estimates on sub-tasks in the way a lot of people expect it to work (because there's different ways of doing it and Atlassian have opted to code for none of them)

Suggest an answer

Log in or Sign up to answer
Atlassian Summit 2018

Meet the community IRL

Atlassian Summit is an excellent opportunity for in-person support, training, and networking.

Learn more
Community showcase
Posted Aug 06, 2018 in Jira Service Desk

A is for Activate: Share your top Jira Service Desk onboarding tips for new users!

Hi, everyone! Molly here from the Jira Service Desk Product Marketing Team :).  In the spirit of this month's  august-challenge, we're sourcing stories of Jira Service Desk activation fro...

564 views 25 15
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you