How do I set the duration of a sprint?

This question is in reference to Atlassian Documentation: Tracking your progress

Is it possible to set the duration of a sprint in JIRA software? I am working with 15-day sprints, but cannot find the option to customize the duration.

3 answers

1 accepted

Hi Eduardo,
this feature is available since JIRA 6.7, read more about it in the release notes:

https://confluence.atlassian.com/agile/jira-agile-releases/jira-agile-release-notes/jira-agile-6-7-release-notes

Just search for "Default sprint durations for new sprints".

If your JIRA version is older this is not possible.

 

Problem solved. Thanks for the help!

Hi Eduardo,
if either Michael or my contribution led to your solution it would be great, if you could accept our answers smile

Thanks,
Florian 

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Julia Dillon
Posted Tuesday in Jira

Tell us how your team runs on Jira!

Hey Atlassian Community! Today we are launching a bunch of customer stories about the amazing work teams, like Dropbox and Twilio, are doing with Jira. You can check out the stories here. The thi...

246 views 1 18
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you