How do I remove an issue from a completed sprint?

Hi,

We've got some stories that have accidentally been in previous sprints but were hidden due to their status. These stories have been taken out of the current sprint but show all the previous sprints they were in. This is causing them not to show up on other boards due to some board specific filters. I've changed these filters for now but in the past I was able to just remove the completed sprints from issues using the technique described in - https://community.atlassian.com/t5/Jira-questions/How-do-I-remove-an-issue-from-a-completed-sprint/qaq-p/123077

I've just tried it again and it doesn't seem to be working for me. It lets me change the sprint field to a genuine sprint but seems to no longer be working if I leave it blank, it says it is going to do it but doesn't seem to update anything.

Has anyone come across this problem recently, is this working for other people? 

Thanks.

 

4 answers

I'm having this same issue. It appears to work by showing the bulk action was successful, but the completed sprint still shows up in the sprint field of the ticket. Any update?

Hi I have the same issue too.. anyone the forum please can you post if there is anyway to clear the Completed sprint from the issue in JIRA Cloud.

Thanks,

Manohar

vote to say I am having the same problem, in JIRA Cloud

My current workaround is to clone the issues discarding sprint data. In JIRA Cloud this can be done via CSV export/import or the Clone / Bulk Edit Clone functions.

My current workaround is to clone the issues discarding sprint data. In JIRA Cloud this can be done via a CSV export/import or the Clone function.

0 votes
Mohamed Riza Atlassian Team Sep 13, 2018

Hi @Ciaran Grimes

I attempted to reproduce this issue in Jira 7.11.2, however, doing a bulk edit to an empty value would clear the the sprint field. Can you clarify the version you are using? In addition to this, can you please clarify when you once you go to those issues in the Jira issue view, do they still have the old value of the Sprint, or is this present only in the Issue Navigator while searching? 

@Mohamed Riza

Thanks for the reply. Sorry I should have made it clear, this is in Jira cloud. The behaviour you are describing is exactly what I want - clearing the sprint field - but it appears to not be working anymore (or I'm doing something wrong). I've just done it again to check and the old sprint value is present in the issue view and the issue navigator. 

I've done this quite a few times in the past and it has worked fine so not sure what is going wrong now!

Thanks.

I've managed to remove a closed sprint by bulk editing & changing the sprint to a current open sprint, then remove the sprint value. Bit of a pain as you have to do 2 things to get there but got the result I needed.

Suggest an answer

Log in or Sign up to answer
TAGS

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you