How do I get the gantt feature to utilize Due Dates instead of release date for JIRA Portfolio?

I already have all my due dates set in JIRA and I need to have a gantt chart to read off of those due dates for upper management. How do I change this? 

1 answer

2 votes

Hi Brittney, unfortunately this is not possible in JIRA Portfolio. The goal of the tool is to help you come up with realistic (forecasted) end dates of initiatives, epics and stories based on teams' availabilities and the estimates, and these are the dates displayed in the chart. You can go the other way, i.e. have Portfolio help you determine the date and then set it as a due date on the issue, but not vice versa. 

Could portfolio check if the due-dates on the issues assigned to a release are violated by the calculated release date?

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Jan 08, 2019 in Jira

How to Jira for designers

I’m a designer on the Jira team. For a long time, I’ve fielded questions from other designers about how they should be using Jira Software with their design team. I’ve also heard feedback from other ...

1,234 views 5 10
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you