How can I customize estimation different for each month and not total workload equally diivided for

Saumya Gupta
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 25, 2021

How can I customize estimation different for each month and not total workload equally divided for duration. If I log work or issue and effort estimation it automatically divides the time into equal hours for the months 

Example 100 hrs May to Aug 21 ie 4 months. 

                        May           Jun         Jul      Aug

Jira Default      25h             25h         25h     25h          100/4=25 hrs per month 

Required         10h              40h         40h     10h          tot 100 hours per requirement 

 

How can I add estimation in required form on Jira?

 

Thank you

 

1 answer

0 votes
Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 31, 2021

Hi @Saumya Gupta -- Welcome to the Atlassian Community!

Did you get an answer to your question?  If not, I do not believe this is possible with out-of-the-box Jira features.  There are a couple of related suggestions to improve this, related to using capacity and actual working days remaining:

You could also investigate marketplace apps for purchase that have improved time keeping features: https://marketplace.atlassian.com/search?hosting=cloud&product=jira

Best regards,
Bill