Right now in the agile boards when you go from open to in progress it will assign the issue to the user who changed the status by default. Is there a way to go to unassigned if the issue is changed back to open?

1 answer

1 accepted

1 vote
Answer accepted
Maarten Cautreels
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 3, 2014

Hi Shawn,

You can set this in your workflow. The transition that moves the issue from a certain status back to Open you can add a Post Function named Clear Field. Configure it so the Assignee field is cleared and you should be good to go.

Best,

Maarten

Shawn Lunny April 3, 2014

Where do I declare the post function at? I don't see a field for it. (I am using JIRA ondemand if that matters). Thanks!