aggregatetimeoriginalestimate
timeestimate
timeoriginalestimate
aggregatetimeestimate
aggregateprogress
progress
thanks!
thank you Nic,
which one belongs to the picture below? And how can I change this attribute (Estimated) through the API?
All of them. Estimated is the original estimate, but if it's been changed by a user, you'll be seeing time estimate. Progress accumulates them with the work that has been logged.
and in which way it is possible to change "Estimated" through the API?
mutableIssue.setEstimate(x) will do it.
oh, sorry I have not expressed myself clearly, I am using JIRA REST API and want to change this parameter through POST/PUT by means of curl
Ah, ok, I saw you'd got another question for that specifically, so I popped an answer on that.
Hello Nic,
can you please share me that link.
I mean for this -> Ah, ok, I saw you'd got another question for that specifically, so I popped an answer on that.
I want to use JIRA REST API for getting the remaining estimate(logged) time. If anyone can help here.