Make Due Date a required field in Work Management

Armin Guldalian
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 24, 2022

We are using JIRA Software and JIRA Work Management in our company.  I understand how to make a field required in the former, but I cannot figure out how to make Due Date a required field in Work Management.  Any ideas?

2 answers

1 vote
Fabio Racobaldo _Herzum_
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
November 24, 2022

Hi @Armin Guldalian ,

welcome to the Atlassian community!

Fields management is the same for both module JIRA Software and JIRA Work Management.

Probably your work management project is a team-managed one. In that case you need to make fields mandatory using the following approach https://support.atlassian.com/jira-software-cloud/docs/customize-an-issues-fields-in-team-managed-projects/

Hope this helps,

Fabio

Armin Guldalian
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 24, 2022

Thank you for your help; when I hover over Due Date I get this message:

jirawm.png

0 votes
Rilwan Ahmed
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
November 24, 2022

Hi @Armin Guldalian ,

Welcome to the community !!

if you are looking to make Due date a required field during a transition (example: Open --> In progress), then go to Project settings --> Workflow. Edit the required workflow and add Field Required validator to the transition and then publish the workflow. 

Bernard Van Heuverswyn
Contributor
July 23, 2023

Hi Rilwan, I had the same question, and I found your answer.

I applied it to my workflow (Company Managed) but it only works if you change the status during the Edit of the Issue.
If I move an issue from a column (Kanban) Unplanned to Planned, nothing happens.

Is it possible to make it trigger and open the way if we make the move?

Due Date.jpg

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events