Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Deleted user
0 / 0 points
Next:
badges earned

Your Points Tracker
Challenges
Leaderboard
  • Global
  • Feed

Badge for your thoughts?

You're enrolled in our new beta rewards program. Join our group to get the inside scoop and share your feedback.

Join group
Recognition
Give the gift of kudos
You have 0 kudos available to give
Who do you want to recognize?
Why do you want to recognize them?
Kudos
Great job appreciating your peers!
Check back soon to give more kudos.

Past Kudos Given
No kudos given
You haven't given any kudos yet. Share the love above and you'll see it here.

It's not the same without you

Join the community to find out what other Atlassian users are discussing, debating and creating.

Atlassian Community Hero Image Collage

Dear support,

we have two column names (QA) and Done both set solutions to Done.

but when we click on sprint complete, the system considers the task complete under Done, but the task under QA is pending.

our puros to know that how many tasks we have done in sprint 1 without moving them to the next spring. attach the screenshot. 

I am waiting for your help. 

thanks,

Thary2021-05-26_100001.png

2 answers

1 accepted

0 votes
Answer accepted
John Funk Community Leader May 26, 2021

Hi Sim - Scrum boards do not care what the status is - just that the card is in a status mapped to the last column on the board. There can be multiple statuses in that column, but the card must be there to be considered "Done. 

John Funk Community Leader May 26, 2021

The only way to mark them Done is to move the card to the last column. 

Hi @sim_sisavuthary,

When closing a sprint from a scrum board, only the issues in the rightmost column of your board are considered as done, regardless of anything else.

So if you want issues to be considered closed, they must be in that rightmost column.

It is possible to map multiple statuses from your workflow to that column if that is what you need. That is done in Board Settings > Columns, by dragging statuses to the corresponding columns of your board. 

So we don't have another way to makes tasks as close with multiple card in sprint one without moving them to the next sprint? 

The only way to mark a card as done in a sprint is to put it in the done column.

Done issues will not go to the next sprint.

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Asked in Jira Service Management

JSM June ask me anything (AMA)

Hello Community members! We’re wrapping up the end of JSM June with an Ask Me Anything (AMA) with the Jira Service Management product team. This is your chance to ask all your ITSM questions to o...

270 views 13 14
View question

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you