Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,465,994
Community Members
 
Community Events
176
Community Groups

When I edit manually original estimate field it doesn't edit the Time remaining field

Edited

I have some issues that has an original estimate and sometimes when the time is not enough, after the issue had been worked with logged hours, some hours or time is added in the Original estimate field, manually.  The problem here is that the Time remaining fields doesn't adjust to the new Original estimate. Only in issues with previous logged hours, can you explain why this is happening? Does this action, edit manually the original estimate affects the reports? 

1 answer

0 votes

Hi @Sofia Grunspan,

The expectation is that when you set the original estimate it sets the remaining estimate.  However this only happens the first time, it seems in this situation you would only want to edit the remaining estimate.  This is useful for determining accuracy of how close original estimates are to actual logged time (See time reporting here).  Changing the original estimate after the fact would introduce bias in the data set.

I would just change remaining estimate, no need to update the original estimate.

Cheers,
Nick [Tempo/ALM Works]