Hi, would like to understand if it's possible to extend the time range for timeline in Jira project. As of now it only shows 2 years ahead.
Looked around and cant find information about the issue we experience here.
Cheers Patrik
Hi @Patrik Hoglund,
No, the timeline does not go beyond that point and this is not configurable. In plans (advanced roadmaps) - part of the premium plan - this goes on for years.
Also, in Jira Product Discovery you have a different type of roadmap for ideas, where you can divide work across doing now / next / later. Also an option to deal with work for the farther future.
Looking at a Jira project, where you are basically doing task level planning, why would you need that time horizon? I can't remember ever seeing a detailed planning being accurate across such a long time frame.
Hope this helps!