One project, multiple teams, parallel but different sprints.

My organization is about 60 people, split into various teams, all sharing the same backlog.  Team A doesn't care about Team B's sprint, and so on.  Team A's sprint might have different start and end dates, and so on.  We don't want to split the project into multiple projects based on teams.  We really just want separate boards, with separate and isolated sprints, for each team, all pulling from the same backlog. 

Is this possible within JIRA Agile?  

1 answer

This widget could not be displayed.

Hi Jace, 

Yes, that is possible. You can benefit from the Parallel Sprint JIRA Agile Lab.

To activate it just visit:

  1. Cog icon > Add-ons
  2. JIRA Agile (left menu) > JIRA Agile Labs
  3. Check the Parallel Sprint box

Then, you can just start to create the sprints for each team on their respective Agile board. smile

Let us know if this helps you out. 

Cheers!

How does this impact velocity metrics? is this available in the download version?

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Apr 22, 2018 in Jira Software

How-to setup a secured Jira Software 7.9.0 on Ubuntu 16.04.4 in less than 30 minutes

...PermissionsStartOnly=true User=www-data Group=www-data ExecStart=/opt/jira/bin/startup.sh ExecStop=/opt/jira/bin/shutdown.sh TimeoutStartSec=120 TimeoutStopSec=600 PrivateTmp=true [Install] WantedBy...

1,489 views 10 12
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you