Is there a way to have stories nest under epics under the timeline view in a Next-Gen Project or is this feature unavailable? Our team is curious about this and has not seen a way to enable this if it is possible.
Thank you!
Hello @christian.gralak
Can you confirm for us the type of project you are using?
Go to Projects > View all projects, and find your project in the list. What is shown in the Type column.
Also are you referring to
I ask because stories display under Epics in the basic Timeline view for Team Managed Software project currently, but not for Team Managed Business projects.
Hi @Trudy P Claspill
Thank you so much for the quick reply!
This is a business project so it is safe to say this feature is not available.
Thank you for the confirmation!
There are change requests related to this to which you can add your vote and watch:
https://jira.atlassian.com/browse/JWMCLOUD-415
https://jira.atlassian.com/browse/JWMCLOUD-111