You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
Hello everyone,
I have some problems with this roadmap. For this reason, I would like to ask for your help.
First of all, as you can see in the photo I sent, there are some irregularities with the dates. (You probably guessed that this is how I prepared it)
According to my working system, my project consists of 3 phases.
and they are interconnected. So the second phase should not start before the first phase is finished. or if the first phase cannot be completed on time and I need to move it to a later date, the other phases below should be affected and the date should be adjusted automatically.
If I move the PPMK-1 issue (I'm talking about the time bar), all sub-issues connected to it also move with it.
but I can't do this for issuers with the same level (hierarchy), is it possible to do this?
Also again, it seems that my phase-3 is predicted to end later than both Epic and the PPMK-1 issue (initiative) above it. But even if this will happen, automatically Epic (PPMK-6) and Initiative (PPMK-1) should have the same date as (PPMK-23) and the time should be set automatically.
I hope I was able to explain it as I wanted.
Thanks in advance for your ideas and help.