Help says: "The x-axis displays the last 7 sprints completed by the team."
What if I only want to see the last 5 sprints, or if I want the last 20 sprints?
Not that I know of!
In one of the Jira setups for a client, I think there was an option to choose a date range, which will allow you to configure the velocity chart for selective sprints only, but I think it was an on-premise Jira.
For the cloud Jira, the only way to do that is to create a custom velocity chart in a spreadsheet (not an ideal way of course)
May be someone from the community may know if there is another way.
Thank you. At least good to hear that I am not just too dumb ;-)
Kind regards
Jan