Using the free JIRA plan, it is possible to view the target start and end dates for issue types in the Project Roadmap view? That is, I want to see the gantt-chart-like bars in the roadmap associated with the target date range for epics, stories, tasks, and subtask. I have done this or something similar in the Advanced Roadmap but not the Project Roadmap. I am unsure about if it is possible and how to do it. Any guidance is greatly appreciated.
Hi @C. Andrew Pelzmann and welcome to the community,
While this is not related to the free plan, target start and end dates are currently only visible for epics in the standard roadmap. Watch and vote for this ticket to stay informed: JSWCLOUD-18668.
You are correct that the advanced roadmap does display this information. That is part of the premium plan, but it is an additional tool alongside the standard roadmap you see in your free plan.
Hope this helps!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.