I would like to take a single Epic and add two time frames of work start/end dates to the epic so that it displays twice on the roadmap. Is this possible?
Detailed example:
A team worked on an epic from January 2021 - March 2021. They stopped work on the Epic to focus on other features. Later, additional work for that Epic was needed and they picked it back up from October 2021 - December 2021.
Rather than create two separate Epics, or display one very very long Epic spanning from January - December, can an Epic be split to showcase how the team actually worked?
Hello @Brittany Neudeck
Welcome to the community.
I don't believe this is possible in the native Roadmaps feature. I have not found any way so far to accomplish that sort of split timeline for a single Epic.
We have not found a solution for this. It would be a nice enhancement for Advanced Roadmaps in the future.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Have you opened a support ticket with Atlassian?