If the estimation of the subtasks are sum with the parent task in the velocity?

Tieen Nguyen August 17, 2022

For example, when I have a parent task with 2 subtasks. Each subtask I estimate for 2 and 3 days. The parent task I add 5 days (this is the total est of 2 subtasks). Then, when I check the velocity, if Jira sum the estimation of both the parent task and subtasks to 10 days?

1 answer

1 accepted

0 votes
Answer accepted
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
August 17, 2022

Welcome to the Atlassian Community!

No.  Velocity does not look at the estimates on non-sprint items.  Sub-tasks are a part of their parent story, not sprint items.

For Scrum (and hence velocity calculations), you do not put estimates on sub-tasks.  Jira won't work if you do that.

Tieen Nguyen August 17, 2022

I got that, thank you so much 

Suggest an answer

Log in or Sign up to answer