Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,463,334
Community Members
 
Community Events
176
Community Groups

How to query original estimates for a given day in the past?

Dear all, is there any way to query original estimates for a given day in the past?

project = X AND issuetype in (Bug, Task, Story) AND fixVersion in (“123”) and …. ?

I need to get a sort of 'snapshot' to see the number of story points added over time by the end of each release. 

Thanks for suggestions!

 

Cheers

1 answer

Hi @Marcin Jaworski,

You can take a look at the Version report where scope change is indicated over time, as well as the Sprint report, where details are available at sprint level.

Hope this helps!  