You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
Dear all, is there any way to query original estimates for a given day in the past?
project = X AND issuetype in (Bug, Task, Story) AND fixVersion in (“123”) and …. ?
I need to get a sort of 'snapshot' to see the number of story points added over time by the end of each release.
Thanks for suggestions!
Cheers
Hi @Marcin Jaworski,
You can take a look at the Version report where scope change is indicated over time, as well as the Sprint report, where details are available at sprint level.
Hope this helps!