You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
Hello everyone,
I need to create a dashboard that displays the time completion of all the epics of my overall project.
In my project, I have 5 epics.
For each epic, I have an estimated start and end dates and effective start and end date.
For example,
Start date Epic #1: October 16th
Estimated end date Epic#1: Dec 31st
Effective end date Epic #1: Jan, 5th
If I log in on Jira Dec 1st (47 days from Oct, 16th), I need it to show 61%
If I log into Jira on Jan 10th (and my project is finished yet since 5 days), I need it to show 121%
How could I do that?
Many thanks,
hello