I have an active sprint with 80 or so stories in it at about 92 story points. The burndown chart is not showing the "Remaining Values" (red Line). I have estimation set to Story points. I have other projects showing this graph properly, so I'm confused on why the red line is not showing. I'm using JIRA cloud.
I am using this board to show stories from multiple projects, so not sure if that is an issue or not. Seems like a bug?
Looks like this was a timing issue. Remaining values do not show until a day after you start sprint. I would expect a dot or some "Initial Remaining Value" to show. I think they assume the top of the grey line equals the remaining. 2 days into the sprint, the red line is showing as expected.