Hi team,
we've started using Big Picture for our project scheduling and resource management recently and I've been trying to understand how to pause an on-going Jira tasks if a resource is out of action due to personal leave or has been moved from task 1 to an ad-hoc task 3.
Is there an efficient way of pushing the pending work on that task out by a couple of days/ weeks/ months
Also, is there a way to move issues out if a resource is out on a sick leave, I tried through via the BigPicture --> Admin --> Resource Manager path but when a leave is entered it does not show up on resources tab under a portfolio or a program, please note we use Tempo timesheets for timekeeping
@Anna-BigPicture Could you please advise a better solution
Hi @Kulgaurav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.