You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
In my team we have subtasks for each ticket for definition of done but if we decide we want to move a ticket to 'won't do', we have to manually move all of the subtasks to won't do also.
Is there a work-around in Jira Automation to move all of the subtasks too instead of having to do it manually?
Hi Kira - Welcome to the Atlassian Community!
If you are moving the parent to Won't Do - is that the Status you are moving it to? Or is it the Done status and you are setting the Resolution to Won't Do?
If you have a Status of Won't Do, you can create an automation rule with a trigger for when an issue is moved to Won't Do. Then add a Branch for Sub-tasks. Under the Branch add an action for Transition Issue and select the Won't Do status.
Adding to this...
If it is a Status of "Won't Do", you can find a template for that type of rule in the Automation Library.
When you go to the Automation page click on Library.
In the Library are many template rules. You would want this one:
They use Done in the template. You would need to change that to "Won't Do"