Automation - Clone tasks from source project into target project

Munir Patel May 19, 2021

Hi

When an EPIC is created in Project A then automation triggers and tasks from Project B are cloned under EPIC in Project A. Automation that I created is below. The tasks are created in Project A but EPIC link populated is that of Project B.

Automation.JPG

 

1 answer

1 accepted

4 votes
Answer accepted
Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 19, 2021

That is correct. The cloning process clones the value in the Epic Link field also. You will have to add an action to change the Epic Link in the newly created issue.

Munir Patel May 19, 2021

Got it thanks Trudy for your help