I'm at the sprint capacity summary in Jira Advanced Roadmaps, but when I see the capacity allocation it is showing so much less than what it actually shows in Jira backlog. This is my scenario, It is showing that 60 hours out of 240 hour allocated were estimated but this is not the case, I've got more than 170 hours allocated.
So I go to the capacity details and there are a lot of issues showing 0 hours allocated but when I click on them I can clearly see the original estimate field showing the right amount of time estimated. I know that the original estimate time field is the one that advanced roadmaps takes for hours allocation but is not taking it for some issues while for other it does.
Any clues on this?