I have created a Project Plan in Advanced Road Maps. Is there a way to do the following:
Set it so that the dates automatically update based on the Estimation for the task or if I change a date on one task that it automatically adjusts the start and end dates of other dependency tasks much like Microsoft Project or Smartsheet does. I don't have time to manually update every date for every dependency task or tasks that follow the tasks that I updated the date on. Many times you Microsoft Project or Smartsheet you can change the duration of a task and all tasks that have dependencies on this task automatically adjust without any manual intervention.
Hello Jeanne,
Yes, you are able to use scheduling within Advanced Roadmaps. The scheduler uses the following factors to create a sensible schedule of your team's work items:
Source and how to implement: Scheduling behavior
Additional information on Auto-schedule issues
I hope the information above assists with offloading your current manual workflow.
Regards,
Stephen Sifers
HI Stephen, probably a bit too late but i followed everything you suggested and unfortunately when i change the date of a task it won't automatically modify the ones linked with.
Thanks
Renato