SLA Holidays is Half Day but I can't configure.

glcn91 October 26, 2014

In our country 28/Oct/2014 's holidays is half day  but ı can't configure.I want to configure to holiday is half day,it is possible?

1 answer

0 votes
Charles Wells
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 26, 2014

Because specific daily hours can't be set for days marked as "holidays", one option would be to create a custom calendar for this week. You can then specify the exact hours to track SLAs for each day. You can edit the SLA and switch to this calendar for this week. Afterwards, you can switch back to your former calendar. 

More about creating SLAs and Calendars.