How do I move tasks from one project to another?

Tomer Hadassi
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 7, 2016

We've been using 2 projects on JIRA for a bit but realized that for our scope we're better off managing ourselves in one project. The second one still has about 30 tasks linked to it. How do I get them out of there so I can manage everything in one project with one board in it (And the do the sprints from there)?

1 answer

1 accepted

2 votes
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 7, 2016

Run a filter that includes the ones you want to move.  Use "bulk edit" from the tools menu (you may need check that this is available to you via "admin -> global permissions").  Select "move" and it'll ask you what project to move them to.

Tomer Hadassi
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 7, 2016

Thank you so much!

 

Suggest an answer