during the sprint a some stories got removed from the sprint. is there a way in jira align to identify these stories. basically i want to know which are the stories committed when the sprint was started and were removed from the sprint during the sprint execution or before closing the sprint.
Hello Manish and thank you for your question.
The short answer here is simply no, this level of detail is best served being obtained in the team level tools (in our case typically we see this as Jira).
While Jira Align does track concepts like Velocity, it is not meant to replace the functionality that exists in Jira to understand Sprint level metrics. Jira provides you detailed Sprint Reporting that will demonstrate the movement of Stories into and out of an Active Sprint (even changes in the point values of Stories that are part of that Sprint.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.