Would mapping of an exiting team (Jira Proj) to a new program impact the running PI, with that team?

We have Jira Align and Jira Cloud integrated. Now we are reorganizing the programs, creating new programs and teams (Jira Projects).

Would mapping of an exiting team (Jira Proj) to a new program impact the running PI, with that team?

1 answer

1 accepted

0 votes
Answer accepted
Sam Tsubota Atlassian Team Feb 16, 2021

@Vinay Sharma there isn't an issue with mapping an existing team to a new program. There is a community article on how to do that.  Here is a link to the article. 

https://community.atlassian.com/t5/Jira-Align-articles/Jira-and-Jira-Align-Integration-Migrating-an-integrated-Jira/ba-p/1276573

If the new program does not use the same PIs and anchor sprints as the previous program in Jira Align, you will need to update the Program and PIs assigned to epics, capabilities and features that the team has work linked to in future PIs. In some instances, you may need to create new capabilities and features if multiple teams in the previous program have work linked to them. Also you will need to update the PI field for the team's orphan stories in future PIs that are associated to the old PIs. 

Thanks Sam; this article is very useful.

I could notice the impact of changing the program for a team with running PI.

Mapping a team to a new program was causing team's disappearance from the program board of running PI.

Hence it looks like, will have to wait till closure of the PI or alternatively will have to create a new team. 

Sam Tsubota Atlassian Team Feb 16, 2021

@Vinay Sharma that is correct. If you move a team during the middle of the PI you may see some adverse effects to the reports and views in Jira Align such as what you described with the Program Board.  It is better to make this type of change at the end of a PI as you mentioned. 

Like Vinay Sharma likes this

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Jira Align

Lean Portfolio Management with Jira Align

Lean Portfolio Management (LPM) is a relatively newer management methodology which draws from lean and systems thinking approaches to drive value-based outcomes, as opposed to more traditional techni...

367 views 0 22
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you