Sync of story point between Jira Align and Jira Alter SP value

Morten Christophersen
Contributor
September 4, 2023

When Stories etc are synced from Jira to Jira Align it truncates the SP value into the nearest value of the selected schema. (chosen in Jira Align e.g. 1,2,3,5,8,13,20). This is causing us a headquakes when comparing metrics across platforms. As SP field in Jira is free in format. It would be really nice of it just synced the value without changing it. This is also good practice for a synchronization function anyway.

I fully understand the reason why we do not want to estimate in half SPs and stick to an approx fibonacci scale, but that should be kept in a separate discussion.

Do you know if one can setup the system to use the fibonacci scaled when entering the SP from Jira Align, however if the value comes from Jira then it just takes the values as is, without changing it. - If you then later update the value again from JA you stick to fibonacci scale as selected in the setup of JA.

1 answer

0 votes
Raja Shekher
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 20, 2023

Hi @Morten Christophersen 

Check that 

  1. Log in to JIRA Align as "Admin"
  2. Under Connectors --> JIRA Settings -> "Jira Set up"
  3. Under "Custom Field" -- >Story Points Custom Field check the Sync Direction and make sure the custom field is set.

 

Also make sure that the Fibonacci is set, by following the below steps.

 

  1. Log in to JIRA Align as "Admin"
  2. Click the gear or wheel icon
  3. Under Settings --> Platform

You see "Point System" where you can set Fibonacci or Power of 2.

Hope this helps!

 

Regards,

Raja

Morten Christophersen
Contributor
September 21, 2023

Hi Raja, 

Thanks for taking the time writing:-)

Maybe my description is not clear but this is not my problem. My problem is that in jira when SP are set there (as they in our setup is for 99.9999% of time) Then they can chose whatever decimal number they want to. then when this is synced to Jira Align, the number get rounded. I should just go in unchanged. That would keep numbers in the two system equal.

Raja Shekher
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 21, 2023

Hi @Morten Christophersen - Ah, thanks for clarifying. That is the default feature of JIRA Align. Once the story point is pushed from JIRA to JIRA Align and if there is a decimal number entered in the JIRA then the decimal number will be rounded off to the nearest whole number in JIRA Align.

 

Unfortunately, there is no work around at the moment as the standard of entering the story points is the whole number across the organizations.

 

Regards,

Raja

Morten Christophersen
Contributor
September 21, 2023

Hi, 

 

Yes, I know that the default is integer numbers.But that does not change the fact that a "sync" function should only sync and not change values:-) The metrics are having different results, which ruins confidence in metrics....

Raja Shekher
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 21, 2023

Hi @Morten Christophersen - I understand your concern but I have not seen this Feature as part of their Roadmap but you can raise a request https://support.atlassian.com/contact/ with Atlassian to see if there are any alternatives. I am sorry I couldn't be of much help here.

 

Regards,

Raja