Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,467,821
Community Members
 
Community Events
177
Community Groups

I would like to see a burn down of an initiative at the Portfolio level

I am using the Train Progress report to see the burn down of an initiative. But the initiative is shared between multiple trains. How do I get a holistic view of the burn down at the portfolio level?

3 answers

0 votes
Tina Behers Community Leader Jul 05, 2021

@Ann Bouvier Each Epic (Initiative) also has a handy dandy link on the Initiative/epic under "more options" on the right (work item menu) Called "Initiative Planning" 

This view provides a view of the total burndown for the Initiative, regardless of which ART underlying Jira Epic is associated.  The Caveat - you must, of course, have the Initiative associated to more than one ART/SoS in order to have Jira Epics worked on my more than one ART/SoS. Initiative Burndown.PNG

0 votes
Caz Atlassian Team Jul 16, 2020

@Ann Bouvier you may also go the upper right corner of the Train Progress report and select "Drill Down" , then "View Epics". Here you may see how each Program is burning down by specific epics. Hope this helps :) 

0 votes

Ann, if you change the context in the configuration bar, from your Train up to your Portfolio, it will aggregate the burndown in the PI Progress report.
 Screen Shot 2020-07-09 at 12.38.01 PM.png

but I want to see the burndown for just 1 initiative.  This is not showing that.  

I still see my initiative in multiple trains.

I believe if you mapped your single initiative to a product, you could select that product from the Additional or Advanced Configuration menus, located in the configuration bar. That will add a new dimension and should then narrow the selection.

Screen Shot 2020-07-13 at 10.14.16 AM.png

I dont see Product... What does that map to.  Maybe we renamed something in terminology?

Screen Shot 2020-07-15 at 5.05.39 PM.png

Select the Additional Configurations plus sign, just to the right of your PI (time) dimension.You should then see a dropdown that includes a few additional options that you can filter on. If you have not defined any products, this may not work.