How does Feature Estimation Percentage work in JIRA Align

Bob Hunt
Contributor
January 29, 2025

I'm seeing what seems to be an inconsistency on how Feature Percentage Complete is represented in our project.
I've got a feature that had been split.
After the split the original feature has 16 stories and the new one has 26 stories.

(I'm not sure if the above is relevant or not....)

The Part 2 of the feature shows 33% complete when viewed within the Feature Editing dialog but it shows 25% complete when displayed in the roadmap view.

One of my users is asking why these % completes are different based only on the selected view.

Thanks for the insights!

 

1 answer

0 votes
Allan Maxwell
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
February 10, 2025

There is a setting in Jira Align to determine if you want to see Feature Progress by Story Count of Story Points.  It does not seem to impact the dial on the Feature edit panel, so you may see a different percent complete their then on the Roadmap or Program Room.

 

Screenshot 2025-02-10 at 2.02.49 PM.png

 

-------------------------------------

Screenshot 2025-02-10 at 2.00.58 PM.png