How can I raise parent status when all subtasks are complete?

Döndü Türkmen August 17, 2021

I have an issue type and it has subtasks. When all subtasks are completed, I want to switch my main task to another status. I use Script Runner plugin but i can't success. Is there any other way to do this? Can you help me?

1 answer

1 accepted

Suggest an answer

Log in or Sign up to answer
2 votes
Answer accepted
Guilhem Dupuy
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
August 18, 2021

Hello @Döndü Türkmen ,

You can achieve this using Automation for Jira, which is a free plugin on Jira Data Center.

Using this add-on you can create an automation rule that will change your parent task status when all of its tasks are complete.

Here is an example of automation that would achieve what you want to :

parent automation.png 

 

Let me know if it helps,

 

Guilhem

Döndü Türkmen August 18, 2021

Thank you for help me. 